Calgary

Kinder Morgan Canada appeals to regulator after it fails to gain Burnaby, B.C., permits

Kinder Morgan Canada Ltd. said Thursday that it has been unable to gain permits from the coastal city of Burnaby, B.C., for its Trans Mountain pipeline expansion and is appealing to the national regulator for construction approval.

Burnaby, B.C., has long opposed the expansion over environmental concerns

Kinder Morgan Canada, a unit of Houston-based Kinder Morgan Inc., said in a statement it is also asking the National Energy Board (NEB) regulator to set up a process to make an "expedited determination" for future such cases. In this file photo, pipes are seen at the pipeyard at the Trans Mountain facility in Kamloops, B.C. (Jonathan Hayward/Canadian Press)

Kinder Morgan Canada Ltd. said Thursday that it has been unable to gain permits from the coastal city of Burnaby, B.C., for its Trans Mountain pipeline expansion and is appealing to the national regulator for construction approval.

Burnaby has long opposed the expansion over environmental concerns, and the lack of permits from the city adds to the hurdles facing the $7.4-billion expansion, as North American energy projects face increasing opposition from activists.

The company, a unit of Houston-based Kinder Morgan Inc., said in a statement it is also asking the National Energy Board (NEB) regulator to set up a process to make an "expedited determination" for future such cases.

Such a process is necessary to prevent delays in construction for the expansion, which is scheduled to go online December 2019, the company said.

In an affidavit filed to the NEB, Michael Davies, Kinder Morgan Canada's vice-president for operations, said each month of delay directly costs the company up to $35 million and deprives it of more than $90 million in revenue.

The regulator and the office of the Burnaby mayor did not immediately respond to requests for comment.

While the Trans Mountain expansion has federal approval, it faces opposition from environmentalists, aboriginal groups and provincial and municipal governments in British Columbia where it would terminate.

Company says it worked in 'good faith'

Kinder Morgan said in its Thursday statement it has worked many months and in "good faith" with Burnaby, and that its failure to grant permits raises issues of jurisdiction.

The proposed expansion of the Trans Mountain pipeline from Alberta would nearly triple its capacity to 890,000 barrels per day and significantly increase crude tanker traffic off the West Coast.

Canadian oil producers, whose landlocked product trades at a discount to the West Texas Intermediate benchmark, say they need additional pipeline capacity to fetch better prices.

In other hurdles facing the project, Kinder Morgan has said the expansion's operational start date could be pushed back due to the time taken to obtain provincial permits and the NEB's ban on installing mats that deter fish births along the pipeline route.

Environmental and aboriginal groups have filed for a judicial review that could overturn the project's federal approval.

Federal law will prevail, says expert

Nigel Bankes, the chair of natural resources law at the University of Calgary, said Thursday that Trans Mountain has a valid argument, given its pipeline expansion project already has federal approval. Based on Canadian constitutional law, in the event of an operational conflict between federal approval and a provincial law or municipal bylaw, the federal law will prevail, Bankes said.

"I think we've always known that this would be a long battle," he said. "The city and the municipalities, NGOs and the First Nations were not going to simply take it as a given that this project was a go-ahead, but would continue to fight it every step of the way.

"So people have said, 'well yes, this project has been approved, but it's going to be death by a thousand cuts from here on in.'"

With files from CBC NEWS