Hamilton

Phase 2 contract for Randle Reef cleanup has been awarded: Environment Minister

Canada's Environment Minister Catherine McKenna was back in Hamilton Friday to announce that the contract to dredge the contaminated sediment at Randle Reef and place it in a giant metal box has been awarded.

The cleanup is scheduled to be completed by 2022

Hamilton's Randle Reef is one of the worst coal-tar contaminated sites in Canada. (Samantha Craggs/CBC)

Canada's environment minister Catherine McKenna says one day, she hopes she'll bring her three kids for a swim in Hamilton Harbour.

That day won't be today.

But the federal government has taken another step in cleaning up the water. On Friday, McKenna announced it's awarded the contract for the second phase of the cleanup of Randle Reef, the most contaminated coal tar sediment on this side of the Great Lakes.

Two companies — Milestone Environmental Contracting Inc. and Fraser River Pile and Dredge Inc. — were chosen among four bidders for the $32.9 million contract. 

Right now, crews are building a large steel container around much of the 695,000 cub metres of sediment contaminated with polycyclic aromatic hydrocarbons (PAH) and other toxic chemicals. This next phase, which will start in 2018 and finish in January 2020, involves sucking up the sediment outside it like a vacuum cleaner and depositing it inside.

Environment Minister Catherine McKenna and Bob Bratina, MP for Hamilton East-Stoney Creek, were in Hamilton Friday to announce the contract for phase two of the Randle Reef clean up has been awarded. (Samantha Craggs/CBC)

It's a major step for a project so long in the making that McKenna, a Hamilton native, got tearful just talking about it. 

"It means one day, I will bring my three kids and we will all go swimming in the Hamilton Harbour," she told the audience. 

"This is a remarkably stunning place, and I'm even more proud to call it home when we do things like this."

Randle Reef is a mass of underwater toxic waste off the coast of Stelco. It covers about 60 hectares, or 120 football fields. The federal and provincial governments are contributing to the $139 million cleanup, as well as Hamilton, Burlington, the Hamilton Port Authority and Stelco. It should finish in 2022.

The final phase of the project will involve removing the water from the sediments in the containment area and placing an impermeable cap on the facility, sealing in the contaminants.

Catherine McKenna, a Hamilton native, got tearful thinking about Randle Reef being finished, which would lead to a more swimmable harbour. (Samantha Craggs/CBC)

The spill originates from a coal gasification plant that was in the city back in the 1800s, and was compounded by years of industry pollution.

The next phase involves hydraulically dredging the sediment through an underwater pipeline, said Dave Lawrence, project manager of Public Services and Procurement Canada.

Lake Ontario's current high water levels have delayed crews installing tie rods on the current phase, Lawrence said. But they expect to catch up once water levels drop.

The steel box has a lifespan of about 200 years.

Work on Randle Reef is expected to be completed in 2022. Lake Ontario's high water levels delayed some work on the current phase, says the project manager, but not the project as a whole. (Samantha Craggs/CBC)

Randle Reef is named after Captain Harvey T. Randle who was a marine pilot with the Hamilton Harbour Commission and was, in 1964, stranded on the reef.

McKenna said Hamilton Harbour has "been totally transformed since I was a kid." She remembers a time when no one even walked along the water. Now, Hamilton's waterfronts are bustling with activity.

McKenna even referred back to a Liberal move in the early 1990s, when former Hamilton MP and environment minister Sheila Copps donned a wetsuit and swam in the harbour to show people it was possible. 

"I do hope one day I will be able to swim out here," she said. "But I don't do wetsuits."

The design plan for constructing a containment area in Randle Reef. The walls are expected to be completed in 2017. (Chris Seto/CBC)