Bishop Grandin bike bridge, transit upgrades on hold
Shortage of provincial funding leads city to cancel eight projects, report says
Winnipeg plans to put off construction of a $12.5-million bike-and-pedestrian bridge over Pembina Highway and $6 million worth of transit upgrades because it no longer expects the province to help pay for the projects.
The city is no longer planning to ask Ottawa to help build the Bishop Grandin Walk Bike Bridge over Pembina near University Crescent, according to a report published by the city on Friday. The bike-and-pedestrian bridge is intended to complete the Bishop Grandin Greenway and make it safer for cyclists to reach Investors Group Field and the University of Manitoba's Fort Garry campus.
The city is also abandoning plans to ask the Trudeau government for help paying for seven Winnipeg Transit projects, including new buses and shop-equipment upgrades.
- Bridge a 'game changer' for Winnipeg cyclists, city councillor says
- Winnipeg faces $6.3M budget hole due to end of provincial deals to fund police and transit
In the same report, Taylor recommends council approve $35 million for other projects that would require Ottawa to cover 50 per cent of the cost.
Those projects include $13 million worth of protected bike lanes, $11 million worth of sewer upgrades, a $7-million bike-and-pedestrian upgrade to the bridge over the Red River at Chief Peguis Trail and a $3-million rapid-transit master plan and prioritization study.
The city would have to borrow money to cover half the cost of the transit study, but would pay cash for the other new projects, Taylor writes in the report.
South Winnipeg-St. Norbert Coun. Janice Lukes said while she's disappointed to see the city back away from building a bike-and-pedestrian bridge in her ward, she's more upset most councillors had no input into the decision to abandon eight projects but pursue seven others.
"You're asking council to vote on a $34-million investment and you haven't told half of council why the prioritization is what it is," Lukes said Sunday in a telephone interview.
"The point of that is depoliticize the choice of these projects, keeping in mind all of them are subject to federal funding," Morantz said Sunday in a phone interview.