The opening of the new Saint John Law Courts building at Peel Plaza will be delayed after problems were discovered with the heating equipment.

A malfunction with the heating system caused pipes to burst on Sunday

Building opening delayed

12 years ago
Duration 1:51
The opening of the new Saint John Law Courts building at Peel Plaza will be delayed after problems were discovered with the heating equipment

The opening of the new Saint John Law Courts building at Peel Plaza will be delayed after problems were discovered with the heating equipment.

The Department of Justice confirmed the delay after the problems were found.

A government spokesperson said a malfunction on Sunday night caused some pipes to burst, which led to water damage in the building.

The opening of the new Saint John Law Courts is being delayed after problems were found with the heating system.

Officials were able to secure the former courtroom facilities at city hall, Charlotte Street and Sydney Street for the time being.

Meanwhile, the building’s contractor is working with its insurance company to evaluate the damage.

The $42-million Peel Plaza project has been a controversy for several years in Saint John.

The complex also includes the new headquarters for the Saint John Police.