Metrolinx considering alternate supplier amid court battle with Bombardier
Talks with an unnamed company designed to ensure 'the urgent supply' of vehicles for the Eglinton Crosstown
Ontario transportation agency Metrolinx says it has been in discussions with an alternate light rail vehicle supplier as it continues a court battle with manufacturer Bombardier.
Metrolinx, which helps co-ordinate transportation in the greater Toronto and Hamilton area, said in an Ontario court filing Thursday that talks with an unnamed supplier are designed to ensure "the urgent supply" of vehicles for the Eglinton Crosstown line in Toronto.
- Transport minister fires back at Bombardier for court injunction against Metrolinx
- Metrolinx files notice to terminate Bombardier contract worth over $700M
- 'Put up or shut up' Metrolinx's message to Bombardier, says transit advocate
It noted the number of potential suppliers is limited because it would have to comply with Canadian content requirements.
Metrolinx submitted the lengthy legal document, including affidavits, in response to an injunction filed last month by Bombardier that aims to prevent the provincial agency from terminating its $770-million contract for 182 vehicles.
It alleges that Bombardier (TSX:BBD.B) has repeatedly failed to deliver a prototype vehicle on time for the scheduled 2021 opening of the $5.3-billion line, citing deficiencies in Bombardier's operations in Mexico and Thunder Bay, Ont.
Metrolinx says Bombardier's injunction effort is a tactic to force it into months of litigation that would make it impossible for another supplier to provide the vehicles in time.
Bombardier responded by saying it rejects the allegations made by Metrolinx. The Montreal-based company says Metrolinx's reasons for wishing to end the contract have nothing to do with its ability to deliver.
Bombardier said in statement that it is able to deliver the vehicles on time by November 2018, well before the Eglinton Crosstown tracks are even built.
It says Metrolinx has refused to inspect the pilot vehicle since October and won't use a dispute resolution process included in the contract.