NL

Crew begins laying subsea Maritime Link cable off Cape Ray

​The company responsible for installing what will be the longest submarine electricity cable in North America has begun work off southwest Newfoundland.

Emera N.L. says Maritime Link installation to be completed by end of summer, 2017

This Norwegian vessel is being used to transport the 5,500 tonne subsea cable. The Maritime Link transmission line is being built by Emera to bring Muskrat Falls power to mainland Canada. (Submitted by Emera NL)

The company behind the $1.7-billion Maritime Link project — which will bring Muskrat Falls power to mainland Canada — says crews have begun laying a high-voltage subsea transmission line between Newfoundland and Nova Scotia.

According to a statement by Emera Newfoundland and Labrador on Thursday, the first of two subsea cables arrived in St. John's aboard the vessel Skagerrak from Norway, while a second cable is expected in mid-May from Japan.

This reel of cable arrived in St. John's aboard the Norwegian vessel Nexans Skagerrak. Crews began laying the subsea line off Cape Ray Thursday. (Submitted by Emera NL)

A spokesperson for the company told CBC News that crews left Cape Ray Thursday morning, and were headed towards Point Aconi, N.S.

"The arrival of the submarine cables is the result of more than three years of dedication to safety and quality by our team," said Rick Janega, CEO of Emera. He said the project is on track to be completed later this summer. 

Both cables span 170 kilometres and will be installed across the Cabot Strait, while more than 300 kilometres of overland transmission lines will be laid across the island. 

According to Emera, each cable weighs 5,500 tonnes and, together weigh more than the Eiffel Tower. The line will be the longest of its kind in North America.